Precedence Diagramming Methods: Amazing Tools To Keep Track Of Project Activities

Project Schedule Network Diagram

 

 

Earlier, I talked about all that you need to know about the activity list for projects. In this article, I want to look at all that you need to know about the precedence Diagramming method for projects. Follow me as we will look at that together in this article.

 

 

 

 

The precedence diagramming method is a project schedule network Diagramming method that uses rectangular boxes or nodes to represent boxes or nodes represent activities and arrows to represent precedence relationships between activities.

 

 

This type of diagram:

  • Always reads from left to right.
  • Show duration only in the node.
  • It May be created manually or with software
  • May report a group of related activities as an aggregate activity
  • May use all Precedence relationship types.

 

Summary activities

A summary activity is a group of related activities that, for reporting purposes, is shown as a single aggregate activity in a bar chart or graph. It may also be called a hammock activity.

 

 

Some summary activities have their own internal sequence of activities but others include separate activities.

 

 

Conditional diagramming methods…

Activity sequences that must be revisited or repeated is called loops, while activities that will be implemented only under specific conditions are called conditional branches.

 

A conditional Diagramming method is any network Diagramming method that allows for no sequential activities such as loops or conditional branches.

 

 

Typically, activities in these types of diagrams are represented by rectangles, decision points are represented by diamonds and directional flows as indicated by arrows.

 

Conditional Diagramming methods vary based on the method used. The most common ones is the Graphical Evaluation Review Technique (GERT) and system dynamic models.

 

 

When creating a network diagram, you may want to create a “Start” node that connects by arrows to all the nodes for activities with no dependencies.

 

Do you enjoy this article, add Our Posts to your Reading List.

Action Point
PS: If you would like to have an online course on any of the courses that you found on this blog, I will be glad to do that on individual and corporate levels, I will be very glad to do that I have trained several individuals and groups. They are doing well in their various fields of endeavour. Some of those that I have trained include staff of Dangote Refinery, FCMB, Zenith Bank, and New Horizons Nigeria among others. Please come on Whatsapp and let’s talk about your trainingYou can reach me on Whatsapp HERE. Please note that I will be using Microsoft Team to facilitate the training.

I know you might agree with some of the points that I have raised in this article. You might not agree with some of the issues raised. Let me know your views about the topic discussed. We will appreciate it if you could drop your comment. Thanks in anticipation.

 

Fact Check Policy

CRMNuggets is committed to fact-checking in a fair, transparent and non-partisan manner. Therefore, if you’ve found an error in any of our reports, be it factual, editorial, or an outdated post, please contact us to tell us about it.

 

Become Part Of our Fan Base on Facebook. Click Here.
Follow Us on Twitter. Click Here.
Many Crypto. One place. Use Roqqu

Hi, I now use RavenBank to send, receive and save money. I also pay my bills with ease, you should try it out too

  
Fact Check Policy
truehost
telegram
CRMNuggets Whatsapp Channel
About Adeniyi Salau 1500 Articles
Adeniyi Salau is a highly dedicated and committed Blogger of repute. He likes sharing his IT knowledge with others. My desire is to impact as many lives as possible with my IT skills. You can download my mobile APP. Download the ICTLOAD APP on Google Playstore. Thanks.

Be the first to comment

Leave a Reply

Your email address will not be published.


*