Standard Schedule Diagramming Notations For Projects

Notations For Projects

 

I have talked about all that you need to know about the work breakdown structure for projects. In this article, I want to talk about Standard Schedule Diagramming Notations for projects. Follow as we will look at them together in this article.

 

 

Now the notations…

#1 Early Start

This denotes the earliest time an activity can start. usually, the ES of the first activity in a network diagram is zero. The Early Start of all other activities in the latest Early Finish of any predecessor activities. 

#2 Early Finish 

This denotes an Early Finish. The earliest time an activity can finish. The EF for the first activity is the same as its duration. For all other activities, EF is the latest EF of all the predecessor activities of an activity plan and its duration. 

#3 Late Finish

This denotes Late Finish. It is the latest time an activity can finish. The late Finish for the activity is the same as its Early Finish time. The LF for any predecessor activity is the earliest Late Start of any of its successor activities.

Late Start

This is the latest time an activity can start. The LS for the last activity is its Early Finish minus its duration. The Late Start for any predecessor activity is its Late Finish minus its duration.

Duration

This is the number of work periods required for the completion of an activity.

Do you enjoy this article, add Our Posts to your Reading List.

Fact Check Policy

CRMNuggetsis committed to fact-checking in a fair, transparent, and non-partisan manner. Therefore, if you’ve found an error in any of our reports, be it factual, editorial, or an outdated post, please contact us to tell us about it.

Become Part of our fan base onFacebook. Click Here.
Follow Us on Twitter.Click Here.
Many Crypto. One place. UseRoqqu

Hi, I now use RavenBank to send, receive, and save money. I also pay my bills with ease,you should try it out too

PEOPLE ALSO READ:  Excel Project Management: Optimize Your Workflow Using These Strategies

OUR MISSION

To create well-reached content that will increase the intellectual prowess of our readers.

OUR VISION

To become a reference point in the blogging space by the year 2030. We want to be among the first 30 blogs in Nigeria.

Official Social Media Pages for crmnuggets.com

To Get Email Updates when we post new content, Click Here.

truehost
telegram
CRMNuggets Whatsapp Channel
About Adeniyi Salau 1549 Articles
Adeniyi Salau is a highly dedicated and committed Blogger of repute. He likes sharing his IT knowledge with others. My desire is to impact as many lives as possible with my IT skills. You can download my mobile APP. Download the ICTLOAD APP on Google Playstore. Thanks.

Be the first to comment

Leave a Reply

Your email address will not be published.


*