How To Identify Critical Path For Projects

How To Identify Critical Path For Projects
Sometimes, the resources you are counting on may not be available when they are scheduled to be. How do you know when your project cannot be successfully completed? In this article, we want to thank about some of the ways to identify critical path for projects.
The answer is that you must identify the critical path when developing the project schedule. In this article, I want to talk about how to identify the critical path for projects.
Identifying the critical path allows you to determine which activities have scheduling flexibility before you complete your project schedule.
Critical activities
Critical activities are the activities that are on the critical path. Generally, for all activities along the critical path, ES=LS and ES=LF.
There can be no flexibility in the start time or the finish time for these activities. Activities that are not on the critical path usually have some flexibility in their start and finish dates.
How to identify the critical path…
To identify the critical path for a project with FS precedence relationships:
#1 Conduct Forward Pass
You need to conduct a forward pass to determine the ES and EF for each activity:
- Use zero for the first activity’s ES.
- Enter the first activity’s duration as its EF.
- Calculate the ES for each successor activity when using the largest EF from any of its predecessor activities plus or minus any leads or lags.
- Calculate the EF for each successor activity by adding its duration to its ES.
- Move through all the activities until you have an ES and EF for each one.
#2 Backward pass
You need to perform a backward. pass to determine the LS and LF for each activity.
- Enter the last activity’s EF as it’s LF time.
- Subtract the last activity’s duration from its EG to determine its LS.
- Calculate the LF for each predecessor activity using the earliest LS from any of its successor activities plan or minus any leads or lags.
- Calculate the LS for each activity by subtracting its duration from its LF.
- Move backwards through all activities until you have the LF and LS for each one.
#3 Calculate float
Calculate float:
- For each activity, subtract its EF from its LF to determine the total float.
- For each string of activities with float, calculate the free float for the last activity in the string by subtracting its EF from its successor activity ES.
#4 Identify Critical path
You need to identify the critical path as the path with the longest duration and zero float.
Other factors…
- The ES for the first activity is 0.
- The EF for the first activity in its ES plus its duration.
- The ES of all successor activities is the latest EF of any of its predecessor activities plus or minus any leads or lags between the two activities.
- The EF or all subsequent activities is its ES plus its duration.
- The LF for the last activity is the same as its EF time.
- The LS for the last activity is its EF minus its duration.
- The LF for any predecessor activity is the same as the earliest LS of any of its successors plus or minus any leads or lags between the two activities.
- The LS of any predecessor activity is its LF minus its duration.
- Only the three activities are not on the critical path.
- Only the last activity in the last string has free float.
- The critical path is indicated by bold lines with arrows and includes activities along the path.
Action Point
PS: If you would like to have an online course on any of the courses that you found on this blog, I will be glad to do that on an individual and corporate level, I will be very glad to do that because I have trained several individuals and groups and they are doing well in their various fields of endeavour. Some of those that I have trained include staff of Dangote Refinery, FCMB, Zenith Bank, and New Horizons Nigeria among others. Please come on Whatsapp and let’s talk about your training. You can reach me on Whatsapp HERE. Please note that I will be using Microsoft Team to facilitate the training.
I know you might agree with some of the points that I have raised in this article. You might not agree with some of the issues raised. Let me know your views about the topic discussed. We will appreciate it if you can drop your comment. Thanks in anticipation.
Fact Check Policy
CRMNUGGETS is committed to fact-checking in a fair, transparent and non-partisan manner. Therefore, if you’ve found an error in any of our reports, be it factual, editorial, or an outdated post, please contact us to tell us about it.
Follow Us on Twitter. Click Here.
Many Crypto. One place. Use Roqqu
Hi, I now use RavenBank to send, receive and save money. I also pay my bills with ease, you should try it out too
|