Standard Schedule Diagramming Notations For Projects (+Examples)

I have talked about all that you need to know about the work breakdown structure for projects. In this article, I want to talk about Standard Schedule Diagramming Notations for projects. Follow as we will look at them together in this article.

Now the notations…

#1 Early Start

This denotes the earliest time an activity can start. usually, the ES of the first activity in a network diagram is zero. The Early Start of all other activities in the latest Early Finish of any predecessor activities. 

#2 Early Finish 

This denotes an Early Finish. The earliest time an activity can finish. The EF for the first activity is the same as its duration. For all other activities, EF is the latest EF of all the predecessor activities of an activity plan its duration. 

#3 Late Finish

This denotes Late Finish. It is the latest time an activity can finish. The late Finish for the activity is the same as its Early Finish time. The LF for any predecessor activity is the earliest Late Start of any of its successor activities.

Late Start

This is the latest time an activity can start. The LS for the last activity is its Early Finish minus its duration. The Late Start for any predecessor activity is its Late Finish minus its duration.

 

Duration

This is the number of work periods required for the completion of an activity.

Fact Check Policy

CRMNuggets is committed to fact-checking in a fair, transparent, and non-partisan manner. Therefore, if you’ve found an error in any of our reports, be it factual, editorial, or an outdated post, please contact us to tell us about it.

Become Part Of our Fan Base on Facebook. Click Here.
Follow Us on Twitter. Click Here.
Many Crypto. One place. Use Roqqu

Hi, I now use RavenBank to send, receive and save money. I also pay my bills with ease, you should try it out too

OUR MISSION

To create well-reached contents that will increase the intellectual prowess of our readers. 

OUR VISION

To become a reference point in the blogging space by the year 2030. We want to be among the first 30 blogs in Nigeria. 

Official Social Media Pages for crmnuggets.com

To Get Email Updates when we post new content, Click Here.

Related Posts

Proper Instant Messaging Security Measures
One of the avenues where users can become a victim...
Read more
Top PMBOK 7 PMP Questions And Answers
  The Project Management Professional (PMP) certification is a widely recognized...
Read more
MT Digital Marketing: Unlocking Online Success
    MT Digital Marketing is a digital marketing agency that specializes...
Read more
Gratitude. RCCG Sunday School Teachers.
  OPENING PRAYER: Lord Jesus, help me to be grateful. (Scroll...
Read more
Destiny Destroyers. RCCG Sunday School Manual.
TOPIC: DESTINY DESTROYERS SUNDAY SCHOOL HYMN 1. O Sunday School, on the...
Read more
Understanding Security Policy Regulations And Standards
Business policies are the guidelines that are developed by an...
Read more
Consecration. RCCG Sunday School Manual.
  Memory Verse: For Moses has said, Consecrate yourselves today to...
Read more
Organising Effective Digital Strategy: How To Go...
Organising Effective Digital Strategy: How To Go About It (+Examples)   ‘By...
Read more