Scope Creep Mid-Sprint

⏱ 7 min ⭐ 150 XP 🔁 3 attempts allowed

What you'll do

Choose the best course of action for this Agile scenario.

Scenario

Halfway through the sprint, a stakeholder asks the team to add a new feature. What should the team do?

Ready to try it?