Team Overcommits

⏱ 7 min ⭐ 150 XP 🔁 3 attempts allowed

What you'll do

Choose the best course of action for this Agile scenario.

Scenario

The team wants to commit to 40 points when their average velocity is 25. What should the Scrum Master suggest?