6 Terms Relating To Schedule Management For Projects (+Examples)

This article explains some of the terms relating to Schedule Management 

 

Earlier, I talked about Standard Schedule Diagramming Notations for projects. In this article, I want to talk about six terms relating to schedule management for projects. Follow me as we will look at these terms together in this article.

 

 

 

#1 The Critical Path

The critical path is the network path that has the longest duration. Activities on the critical path cannot be displayed or the whole project will be delayed unless subsequent activities are shortened.

 

 

The critical path is calculated by doing a forward pass to calculate the Early Start and Early Finish for each activity and then a backward pass to calculate the Late Start and Late Finish for each activity. The path with the longest duration and no scheduling flexibility is the critical path.

 

 

#2 Float

Float is the amount of time an activity can be delayed from its Early Start without delaying the project finish date or the consecutive activities. Float occurs only in activities that are not on the critical path. Float is also called slack. There are two types of floats: Total and Free.

 

 

#3 Total Float

Total float is a type of float where the total amount of time an activity requires can be delayed without delaying the project finish date.

 

The total float for an activity can be calculated by subtracting its Early Finish from its Late Finish or its Early Start from its Late Finish.

 

Please note that when you see the term float by itself, it generally refers to total float.

 

#4 Free Float

Free float is the amount of time an activity can be delayed without delaying the Early Start of any activity that immediately follows it. It allows flexibility of the start or finish time within the activity only.

 

 

If there is a string of activities with float, free float will be available only at the end of the string.

 

Free Float for an activity is calculated by subtracting the Early Finish of the activity from the Early Start of its successor activity.

 

Do you enjoy this article, add Our Posts to your Reading List.

To Get Email Updates when we post new contents, Click Here.

Related Posts

Beware Of False Ministers. RCCG Sunday School...
  TOPIC: Beware Of False Ministers    MEMORY VERSE: “But there were false prophets also...
Read more
The Lying Tongue. RCCG Sunday School Manual
  BIBLE PASSAGE: Acts 5:1-10 But a certain man named Ananias, with...
Read more
Day 35: 2023 MFM 70 Days Fasting...
MFM 70 Days Fasting Devotional Songs  Praise and Worship Prayers of Praise...
Read more
Day 15: 2021 MFM 70 Days Prayers...
Day 15: 2021 MFM 70 Days Prayers And Fasting     Devotional Songs  Praise...
Read more
Day 29: 2022 MFM 70 Days Fasting...
  Devotional Songs Praise and Worship Prayer of Praise and Thanksgiving      225. The weapons...
Read more
Utility And Warranty In ITIL 4: Analysing...
  In my previous article, I 7 Major Components Of Service...
Read more
Alternative Spirituality. RCCG Sunday School Manual.
    MEMORY VERSE: “Regard not them that have familiar spirits, neither...
Read more
12 Common Mistakes When Building An E-Commerce...
    In my previous articles, I have looked at some of...
Read more