Identifying Critical Path For Projects: Removing Obstacles To Project Success.

Critical Path For Projects

Ways Of Identifying The Critical Path For Projects

 

 

Sometimes, the resources you are counting on may not be available when they are scheduled to be. How do you know when your project cannot be successfully completed? In this article, we want to thank about some of the ways to identify the critical path for projects. 

 

The answer is that you must identify the critical path when developing the project schedule. In this article, I want to talk about how to identify the critical path for projects.

 

 

Identifying the critical path allows you to determine which activities have scheduling flexibility before you complete your project schedule.

 

 

Critical activities 

Critical activities are the activities that are on the critical path. Generally, for all activities along the critical path, ES=LS and ES=LF.

 

There can be no flexibility in the start time or the finish time for these activities. Activities that are not on the critical path usually have some flexibility in their start and finish dates.

 

How to identify the critical path…

To identify the critical path for a project with FS precedence relationships: 

 

#1 Conduct Forward Pass

You need to conduct a forward pass to determine the ES and EF for each activity:

 

  • Use zero for the first activity’s ES.
  • Enter the first activity’s duration as its EF.
  • Calculate the ES for each successor activity when using the largest EF from any of its predecessor activities plus or minus any leads or lags. 
  • Calculate the EF for each successor activity by adding its duration to its ES.
  • Move through all the activities until you have an ES and EF for each one. 

 

#2 Backward pass

You need to perform a backwards. pass to determine the LS and LF for each activity.

  • Enter the last activity’s EF as it’s LF time.
  • Subtract the last activity’s duration from its EG to determine its LS.
  • Calculate the LF for each predecessor activity using the earliest LS from any of its successor activities plan or minus any leads or lags.
  • Calculate the LS for each activity by subtracting its duration from its LF.
  • Move backwards through all activities until you have the LF and LS for each one.

 

#3 Calculate float

Calculate float:

  • For each activity, subtract its EF from its LF to determine the total float.
  • For each string of activities with float, calculate the free float for the last activity in the string by subtracting its EF from its successor activity ES.

 

#4 Identify Critical path

You need to identify the critical path as the path with the longest duration and zero floats.

 

Other factors…

  • The ES for the first activity is 0.
  • The EF for the first activity in its ES plus its duration.
  • The ES of all successor activities is the latest EF of any of its predecessor activities plus or minus any leads or lags between the two activities.
  • The EF or all subsequent activities is its ES plus its duration.
  • The LF for the last activity is the same as its EF time.
  • The LS for the last activity is its EF minus its duration.
  • The LF for any predecessor activity is the same as the earliest LS of any of its successors plus or minus any leads or lags between the two activities.
  • The LS of any predecessor activity is its LF minus its duration.
  • Only the three activities are not on the critical path.
  • Only the last activity in the last string has free float.
  • The critical path is indicated by bold lines with arrows and includes activities along the path.

Do you enjoy this article, add Our Posts to your Reading List.

Action Point

PS: I know you might agree with some of the points that I have raised in this article. You might not agree with some of the issues raised. Let me know your views about the topic discussed. We will appreciate it if you could drop your comment. Thanks in anticipation.

Fact Check Policy

CRMNuggets is committed to fact-checking in a fair, transparent and non-partisan manner. Therefore, if you’ve found an error in any of our reports, be it factual, editorial, or an outdated post, please contact us to tell us about it.

 

Become Part Of our Fan Base on Facebook. Click Here.
Follow Us on Twitter. Click Here.
Many Crypto. One place. Use Roqqu

Hi, I now use RavenBank to send, receive and save money. I also pay my bills with ease, you should try it out too

 

OUR MISSION

To create well-reached contents that will increase the intellectual prowess of our readers. 

OUR VISION

To become a reference point in the blogging space by the year 2030. We want to be among the first 30 blogs in Nigeria. 

Official Social Media Pages For Crmnuggets.Com

 

Join Our Telegram Channel: CRMNUGGETS

Twitter: @cehnigeria
​Facebook: @CRMNuggets
Instagram: @crmnigeriablog
Pinterest: CEHNIGERIA

Threads @crmnuggets

 
Fact Check Policy
truehost
telegram
CRMNuggets Whatsapp Channel
About Adeniyi Salau 1502 Articles
Adeniyi Salau is a highly dedicated and committed Blogger of repute. He likes sharing his IT knowledge with others. My desire is to impact as many lives as possible with my IT skills. You can download my mobile APP. Download the ICTLOAD APP on Google Playstore. Thanks.

Be the first to comment

Leave a Reply

Your email address will not be published.


*