Standard Schedule Diagramming Notations For Projects

 

I have talked about all that you need to know about the work breakdown structure for projects. In this article, I want to talk about Standard Schedule Diagramming Notations for projects. Follow as we will look at them together in this article.

 

 

Now the notations…

#1 Early Start

This denotes the earliest time an activity can start. usually, the ES of the first activity in a network diagram is zero. The Early Start of all other activities in the latest Early Finish of any predecessor activities. 

#2 Early Finish 

This denotes an Early Finish. The earliest time an activity can finish. The EF for the first activity is the same as its duration. For all other activities, EF is the latest EF of all the predecessor activities of an activity plan and its duration. 

#3 Late Finish

This denotes Late Finish. It is the latest time an activity can finish. The late Finish for the activity is the same as its Early Finish time. The LF for any predecessor activity is the earliest Late Start of any of its successor activities.

Late Start

This is the latest time an activity can start. The LS for the last activity is its Early Finish minus its duration. The Late Start for any predecessor activity is its Late Finish minus its duration.

Duration

This is the number of work periods required for the completion of an activity.

Do you enjoy this article, add Our Posts to your Reading List.

Fact Check Policy

CRMNuggetsis committed to fact-checking in a fair, transparent, and non-partisan manner. Therefore, if you’ve found an error in any of our reports, be it factual, editorial, or an outdated post, please contact us to tell us about it.

Become Part of our fan base onFacebook. Click Here.
Follow Us on Twitter.Click Here.
Many Crypto. One place. UseRoqqu

Hi, I now use RavenBank to send, receive, and save money. I also pay my bills with ease,you should try it out too

OUR MISSION

To create well-reached content that will increase the intellectual prowess of our readers.

OUR VISION

To become a reference point in the blogging space by the year 2030. We want to be among the first 30 blogs in Nigeria.

Official Social Media Pages for crmnuggets.com

To Get Email Updates when we post new content, Click Here.

Related Posts

Determining Website Objectives: What To Look Out...
    In my previous article, I have talked about some of...
Read more
RCCG SOD Year One: Know Yourself. Part...
  You must be like your Father. Your father is a...
Read more
The Expanding Church. Assemblies Of God Sunday...
  The Expanding Church. AG Sunday School Adult Manual   Memory Verse: Romans...
Read more
10 Internet Marketing Techniques For Digital Marketers(+Examples)
10 Internet Marketing Techniques For Digital Marketers     In my previous article,...
Read more
Make Donought Box A Persuasive Marketing Tool...
Do you want to design your doughnut box in a...
Read more
Day 52: 2021 MFM 70 Days Fasting...
Day 52: 2021 MFM 70 Days Fasting And Prayers     Devotional...
Read more
Dynamics Of Grace. RCCG Sunday School Manual.
MEMORY VERSE: “For the grace of God that bringeth salvation...
Read more
Identifying Critical Path For Projects: Removing Obstacles...
Ways Of Identifying The Critical Path For Projects     Sometimes, the resources...
Read more