8/80 Rule For Projects: The Facts You Should Know (+Examples)

Unknown Facts About The 8/80 Rule For Projects

The 8/80 Rule for projects refers to a general guideline regarding work packages; they require more than eight and fewer than eighty hours of effort to be completed.

 

 

The 8/80 Rule help project managers create the work package list by identifying which work components should be considered work packages.

Any work component that can be completed in fewer than eight hours does not rise to the level of a work package.

 

Also, any work component requiring more than 80hours of work is too monumental to be categorised that way.

While the 8/80 Rule may be a useful guide in small projects, it will be impractical to apply it to large projects, which will necessitate tracking millions of work packages.

Activities

An activity is an element of project work packages that requires action to produce a deliverable. Activities lay the foundation for estimating, scheduling, executing, and monitoring and controlling the project work. The characteristics of the activity are:

  • It has an expected duration
  • It consumes budget and human resources.

 

Example:

Some of the activities are:

  • Revising a user manual
  • Making a sales presentation
  • Reserve ng a conference room

Each of these items requires action to produce a deliverable. Each has an expected duration and will consume budget and human resources.

Activity lists …

An activity list is a definitive list of activities that must be completed to produce the desired project deliverables.

 

It includes an activity identifier and a description of the scope of work for each activity so that each team member understands the work required for completion.

PEOPLE ALSO READ:  Project Schedule Network Diagram: Amazing Tool For Keeping Track Of Multiple Projects.

 

The activities in an activity list are listed in sequential order and are used to estimate project duration and create the project schedule.

An activity list for conducting a Training program…

  • Determine training budget
  • Schedule training date
  • Set training requirements
  • Identify trainers
  • Confirm attendees
  • Reserve conference room
  • Set up audio-visual materials
  • Acquire training software
  • Train attendees
  • Collect feedback.

Activity components

Activity can be broken down into smaller components. For example, the activity, Reserve conference room, could be broken down in the following way:

  • Determine size requirement
  • Determine date needed
  • Identify possible room alternatives
  • Select room
  • Call to reserve room
  • File confirmation when received

Activity attributes

Activity attributes obtain additional information about all activities in an activity list.

 

The attribute describes the activities by listing the different components associated with the activities, which include responsible team members and the level of effort required.

 

Activity attributes are used to develop project schedules and select, order, and sort planned activities.

To Get Email Updates when we post new content, Click Here.

Loading

Related Posts

Use Tailwind for Rounded ImagesUse Tailwind for Rounded Images
5 Reasons You Should Use Tailwind for...
 
PEOPLE ALSO READ:  5 Stages Of IT Project Life Cycle (+Examples)
If you're looking for an easy and effective way to...
Read more
kingdom of Godkingdom of God
The Kingdom Of God. RCCG Sunday School...
  RCCG Sunday School Teacher Manual 1 September 2024 TOPIC: The Kingdom...
Read more
Powerful Prayers For Children At HomePowerful Prayers For Children At Home
Powerful Prayers For Children At Home
These are prayers for children in trouble, sick or those...
Read more
victory over satanvictory over satan
Victory Over Satan Part One. RCCG SOD...
    VICTORY OVER SATAN (Part 1)   -An Essential Ingredient To a Miraculous...
Read more
3i principles of digital marketing3i principles of digital marketing
3i Principles Of Digital Marketing: A Practical...
  In order to help you achieve your marketing goals, the...
Read more
Day 28: 2022 MFM 70 Days Fasting And PrayersDay 28: 2022 MFM 70 Days Fasting And Prayers
Day 28: 2021 MFM 70 Days Fasting...
  Devotional Songs  Praise and Worship Prayers of Praise and Thanksgiving    197. Wicked covenants...
Read more
5 Stages Of IT Project Life Cycle5 Stages Of IT Project Life Cycle
5 Stages Of IT Project Life Cycle...
  In my previous article, I have talked about the normal...
Read more
Spiritual Sacrifices: RCCG Sunday School TeachersSpiritual Sacrifices: RCCG Sunday School Teachers
Stand Out. RCCG Sunday School Manual
  Memory Verse: " Wherefore come out from among them and...
Read more
CRMNuggets Whatsapp Channel
truehost

Adeniyi Salau is a highly dedicated and committed Blogger of repute. He likes sharing his IT knowledge with others. My desire is to impact as many lives as possible with my IT skills. You can download my mobile APP. Download the ICTLOAD APP on Google Playstore. Thanks.

2 Comments

Leave a Reply

Your email address will not be published. Required fields are marked *

Enable Notifications OK No thanks