8/80 Rule For Projects: The Facts You Should Know (+Examples)

Unknown Facts About The 8/80 Rule For Projects

The 8/80 Rule for projects refers to a general guideline regarding work packages; they require more than eight and fewer than eighty hours of effort to be completed.

 

 

The 8/80 Rule help project managers create the work package list by identifying which work components should be considered work packages.

Any work component that can be completed in fewer than eight hours does not rise to the level of a work package.

 

Also, any work component requiring more than 80hours of work is too monumental to be categorised that way.

While the 8/80 Rule may be a useful guide in small projects, it will be impractical to apply it to large projects, which will necessitate tracking millions of work packages.

Activities

An activity is an element of project work packages that requires action to produce a deliverable. Activities lay the foundation for estimating, scheduling, executing, and monitoring and controlling the project work. The characteristics of the activity are:

  • It has an expected duration
  • It consumes budget and human resources.

 

Example:

Some of the activities are:

  • Revising a user manual
  • Making a sales presentation
  • Reserve ng a conference room

Each of these items requires action to produce a deliverable. Each has an expected duration and will consume budget and human resources.

Activity lists …

An activity list is a definitive list of activities that must be completed to produce the desired project deliverables.

 

It includes an activity identifier and a description of the scope of work for each activity so that each team member understands the work required for completion.

PEOPLE ALSO READ:  Product Analysis Techniques For Projects: The Various Types (+Examples)

 

The activities in an activity list are listed in sequential order and are used to estimate project duration and create the project schedule.

An activity list for conducting a Training program…

  • Determine training budget
  • Schedule training date
  • Set training requirements
  • Identify trainers
  • Confirm attendees
  • Reserve conference room
  • Set up audio-visual materials
  • Acquire training software
  • Train attendees
  • Collect feedback.

Activity components

Activity can be broken down into smaller components. For example, the activity, Reserve conference room, could be broken down in the following way:

  • Determine size requirement
  • Determine date needed
  • Identify possible room alternatives
  • Select room
  • Call to reserve room
  • File confirmation when received

Activity attributes

Activity attributes obtain additional information about all activities in an activity list.

 

The attribute describes the activities by listing the different components associated with the activities, which include responsible team members and the level of effort required.

 

Activity attributes are used to develop project schedules and select, order, and sort planned activities.

To Get Email Updates when we post new content, Click Here.

Loading

Related Posts

deferred hopedeferred hope
Deferred Hope. RCCG Sunday School Teachers....
 
PEOPLE ALSO READ:  Developing Work Breakdown Structure For Projects: Practical Guide (+Examples)
  SUNDAY SCHOOL HYMN 1. O Sunday School, on the Lord’s day, O...
Read more
CNG And LPG CarsCNG And LPG Cars
CNG And LPG Cars: Why They Are...
  Earlier making the final choice to fix an Autogas structure,...
Read more
Immune System: Diseases, Disorders & FunctionImmune System: Diseases, Disorders & Function
Immune System: Diseases, Disorders & Function
The role of the immune system — a collection of...
Read more
Series 11: Latest CAPM Questions And AnswersSeries 11: Latest CAPM Questions And Answers
Series 11: Latest CAPM Questions And Answers
QUESTION 501 Which of the following characteristics are found in a...
Read more
fulfilling purposefulfilling purpose
Fulfilling Purpose. RCCG Sunday School Teachers.
OPENING PRAYER: Almighty Father, please help me to fulfil the...
Read more
Considerations When Using Paid SearchConsiderations When Using Paid Search
Major Considerations When Using Paid Search: Ways...
There are strategic considerations for when to use paid search,...
Read more
Day 60: 2023 70 Days Fasting And PrayersDay 60: 2023 70 Days Fasting And Prayers
Day 60: 2023 70 Days Fasting And...
Devotional Songs Praise and Worship Prayers of Praise and Thanksgiving      SECTION CONFESSIONS 253. O...
Read more
Ways Of Using Digital Signatures In CybersecurityWays Of Using Digital Signatures In Cybersecurity
Digital Signatures In Cybersecurity: How To Use...
  Digital signatures in cybersecurity are a mathematical techniques used to...
Read more
CRMNuggets Whatsapp Channel
telegram
truehost
About Adeniyi Salau 1578 Articles
Adeniyi Salau is a highly dedicated and committed Blogger of repute. He likes sharing his IT knowledge with others. My desire is to impact as many lives as possible with my IT skills. You can download my mobile APP. Download the ICTLOAD APP on Google Playstore. Thanks.

Leave a Reply

Your email address will not be published.


*