Optimising The Project Schedule: Tips On How To Finish Project On Time.

Project Schedule

 
In my previous articles, I have looked at all that you need to know about the work breakdown structure for projects. In this article, I want to look at all that you need to know about how to optimise the project schedule. Follow me as we will look at that together in this article.
 
 

Now the procedures …

#1 Consider resource-levelling options

There is a need for you to consider the resource levelling options for the project. You have to ask the following questions when you are doing that,
 

  • Can you pull needed resources from activities with float and apply them to critical resources?
  • Can you authorise overtime to meet your project requirements?
  • Is shift still possible?
  • Can an activity be contracted out to free up resources during a critical period?

#2 Consider fast-tracking

There is a need for you to consider fast-tracking the project in order to ensure that the project finishes on time. Ask the following questions when you are going that:

  • Can any activities on the critical path be done concurrently that we originally scheduled sequentially?
  • Are there any discretionary dependencies that could be done completely independently?
  • Are there any increased costs associated with fast-tracking activities?
  • What are the associated links?

 

#3 Analyse activities 

There is a need for you to analyse activities on the critical path to determine if crashing the schedule will produce a viable option. You need to ask the following questions :

  • Are there any activities on the critical path that can be shortened if more resources are added?
  • What are the costs associated with crashing the activities?
  • Which activities will provide the biggest duration decrease while incurring the least amount of incremental cost?
  • What are the resource allocation implications of crashing the activity? Will some key resources be overextended? Will all resources be available when needed?
  • Are there any quality implications associated with crashing the activities?
PEOPLE ALSO READ:  Business Requirements Document: The Major Components (+Examples)

 

#4 Overallocated resources

You need to identify if any resources are overly allocated. You also need to prioritise the project tasks the resources are responsible for and delay those tasks that can be performed later, to avoid over-allocation of resources.
 

#5 Viable scope 

You also need to analyse each of the activities on the critical path to determine whether reducing the scope is a viable option for reducing the duration of the project. 
 

#6 Recalculate critical path 

There is a need for you to regulate the critical path after you have recompressed the schedule. This will help you to know the number of days that you have been able to save after you might have compressed your schedule for the project.

 

#7 Review schedule changes 

Also, you need to review schedule changes with key stakeholders. Since some of them are Subject Matter Experts, it will enable you to get their expert opinions on the subject matter. It will also allow them to be aware of the changes that have been made to the project. 
 

#8 Revise the schedule 

After all your scheduled Compression assignments have been done, you will need to revise the schedule again in order to discover if you have made any mistakes in the course of optimising the project schedule. Once that is confirmed, you have to distribute it to other project stakeholders. 
 
 

Typical example…

You created a draft schedule for your company’s website project. At the draft schedule meeting, the sponsor informs you that the schedule must be compressed by a week so that the new website will go live on time to coincide with a major industry conference.
 
You analyse the critical path and discover that two activities could be performed concurrently, instead of sequentially, you fast-track the activities and gain the needed week, then review the critical path and confirm that it has not been altered. 
 
You review the revised schedule with the project sponsor and obtain approval. The schedule becomes the baseline for the project. 

PEOPLE ALSO READ:  8 Ways Of Gathering Stakeholder Requirements (+Examples)

There is a need for you to gather your preliminary project schedule while including the project’s start and finish dates.

 

Do you enjoy this article, add Our Posts to your Reading List.

Action Point

PS: I know you might agree with some of the points that I have raised in this article. You might not agree with some of the issues raised. Let me know your views about the topic discussed. We will appreciate it if you could drop your comment. Thanks in anticipation.

Fact Check Policy

CRMNuggets is committed to fact-checking in a fair, transparent and non-partisan manner. Therefore, if you’ve found an error in any of our reports, be it factual, editorial, or an outdated post, please contact us to tell us about it.

 

Become Part Of our Fan Base on Facebook. Click Here.
Follow Us on Twitter. Click Here.
Many Crypto. One place. Use Roqqu

Hi, I now use RavenBank to send, receive and save money. I also pay my bills with ease, you should try it out too

 

OUR MISSION

To create well-reached contents that will increase the intellectual prowess of our readers. 

OUR VISION

To become a reference point in the blogging space by the year 2030. We want to be among the first 30 blogs in Nigeria. 

Official Social Media Pages For Crmnuggets.Com

 

Join Our Telegram Channel: CRMNUGGETS

Twitter: @cehnigeria
​Facebook: @CRMNuggets
Instagram: @crmnigeriablog
Pinterest: CEHNIGERIA

Threads @crmnuggets

 

Fact Check Policy

Loading

Related Posts

Day 50: 2023 MFM 70 Days Fasting And PrayersDay 50: 2023 MFM 70 Days Fasting And Prayers
Day 50: 2023 MFM 70 Days Fasting...
   Devotional Songs (Pages 4-12) Praise and Worship
PEOPLE ALSO READ:  Project Management Office Software. A Critique
Prayers of Praise and Thanksgiving...
Read more
List Of Confirmed fake Job Venues In Nigeria 2021List Of Confirmed fake Job Venues In Nigeria 2021
List Of Confirmed fake Job Venues In...
I remember two years ago, I resigned from my job...
Read more
Differences Between A Hacker And A Threat ActorDifferences Between A Hacker And A Threat Actor
Differences Between A Hacker And A Threat...
  We are under attack and attackers want access to our...
Read more
Day 3: MFM 70 Days 2022 Fasting And PrayersDay 3: MFM 70 Days 2022 Fasting And Prayers
Day 3: MFM 70 Days 2021 Fasting...
  Devotional Songs Praise and Worship. Prayers of Praise and Thanksgiving.    85. Eyes of...
Read more
Spiritual Maturity. RCCG Sunday School ManualSpiritual Maturity. RCCG Sunday School Manual
Spiritual Maturity. RCCG Sunday School Manual
  TOPIC: SPIRITUAL MATURITY   BIBLE PASSAGE: Hebrews 5:12-14 [12]For when for the time ye...
Read more
Understanding How Address Resolution Protocol WorksUnderstanding How Address Resolution Protocol Works
Address Resolution Protocol: How It Works
If your network is using the IPv4 communications protocol, the...
Read more
The Disciple as an Eagle. Part One....
The Disciple as an Eagle. Part One   The Bible tells us...
Read more
EzoicEzoic
Christianity and Governance. RCCG Sunday School Teachers
RCCG SUNDAY SCHOOL TEACHER’S MANUAL 17 MARCH 2024 0 FacebookWhatsAppPinterestTwitterMessageShare RCCG SUNDAY SCHOOL...
Read more
CRMNuggets Whatsapp Channel
telegram
truehost
About Adeniyi Salau 1578 Articles
Adeniyi Salau is a highly dedicated and committed Blogger of repute. He likes sharing his IT knowledge with others. My desire is to impact as many lives as possible with my IT skills. You can download my mobile APP. Download the ICTLOAD APP on Google Playstore. Thanks.

Be the first to comment

Leave a Reply

Your email address will not be published.


*