Activity Dependencies For Projects: The Various Types (+Examples)

4 Types Of Activity Dependencies For Projects

 

 

In my previous article, I talked about some of the facts that you need to know about work breakdown Structure for projects. In this article, I want to talk about some of the facts that you need to know about activity dependencies for projects. Follow me as we will look at that together in this article.

 

 

You are the project manager for the launching of a new product line. if you do not understand the sequence in which the project work must occur, you cannot develop an effective schedule. You will end up with rework and additional costs.

 

 

Creating a project schedule network diagram for your project will help you uncover the relationship between risks, and avoid unnecessary work and expense.

 

 

Activity Dependencies

An activity dependency for projects is a logical relationship that exists between two project activities.

 

The relationship indicates whether the start of an activity is contingent upon an event or input from outside activity.

 

 

Activity Dependencies

An activity dependency is a logical relationship that exists between two project activities.

 

 

 

 

The relationship indicates whether the start of an activity is contingent upon an event or inputs from outside the activity.

 

 

Activity Dependencies shape the sequence of project activities.

 

 

Typical example…

An architect, Brian, designed a residence and has a vision for room layouts.

 

However, he will not be able to assess the functionality of the design until the builders frame the structure with walls, windows and a roof.

PEOPLE ALSO READ:  Requirement Documentation For Projects: How To Analyse Project Requirements

 

Once the structure is in place, he will be able to reassess the plan to determine if modifications are necessary.

 

 

#1 Mandatory

A mandatory dependency is inherent to the work itself. It is usually affected by physical constraints. Activities must be performed in a specific sequence for the work to be successful. Mandatory is also known as “hard logic”.

 

#2 Discretionary

A discretionary dependency is defined by the project and the project management team at their discretion. It is defined based on the best practices followed in a specific application area or on specific requirements.

 

If there is no mandatory or external dependency between two activities, the team has some flexibility in activity sequencing.

 

 

It is also known as “soft logic”, “preferential logic” and “preferred logic”.

 

 

For example, the sponsor will like to see the book’s cover design as soon as possible, so the team may decide to have the cover artwork done before the inside illustration.

 

 

#3 External

An external dependency is contingent on inputs from outside the project activities.

 

 

An example is a book that can’t be printed until the shipment of paper arrives.

To Get Email Updates when we post new content, Click Here.

Loading

Related Posts

Latest CAPM Questions And AnswersLatest CAPM Questions And Answers
Series 19: Latest CAPM Questions And Answers
QUESTION 923 Considering a highly dynamic project environment, which approach should...
Read more
Mental Health. RCCG Sunday School Manual.Mental Health. RCCG Sunday School Manual.
Mental Health. RCCG Sunday School Manual.
 
PEOPLE ALSO READ:  Evolution Of E-Commerce: The Categories (+Examples)
Opening Prayer: Father, heal anyone whose health is challenged in...
Read more
Uniqueness Of ProjectsUniqueness Of Projects
Video: Understanding The Uniqueness Of Projects
Action Point   https://youtu.be/f0kUfDLXqPE PS: I know you might agree with some of the...
Read more
image of a leopardimage of a leopard
MFM 70 Days Fasting and Prayer 27...
MFM 70 Days Fasting and Prayer 27 September 2024   MFM 2024...
Read more
Basic Concept Of EntrepreneurshipBasic Concept Of Entrepreneurship
Understanding The Basic Concept Of Entrepreneurship
The word "entrepreneurship" is used to describe the creative, innovative,...
Read more
RCCG SOD Year Five: The Disciple's AnointingRCCG SOD Year Five: The Disciple's Anointing
The Disciple's Anointing. RCCG SOD Year Five.
  THE DISCIPLE'S ANOINTING     We have learnt about different kinds of anointing,...
Read more
The Major Roles Of Customers In a BusinessThe Major Roles Of Customers In a Business
Roles Of Customers In a Business: Why...
Discussing Customers As The Centre The Of Universe     Many CRM definitions...
Read more
CNG And LPG CarsCNG And LPG Cars
CNG And LPG Cars: Why They Are...
  Earlier making the final choice to fix an Autogas structure,...
Read more
CRMNuggets Whatsapp Channel
truehost
About Adeniyi Salau 1749 Articles
Adeniyi Salau is a highly dedicated and committed Blogger of repute. He likes sharing his IT knowledge with others. My desire is to impact as many lives as possible with my IT skills. You can download my mobile APP. Download the ICTLOAD APP on Google Playstore. Thanks.

Be the first to comment

Leave a Reply

Your email address will not be published.


*